Don Armeni Boat Ramp Improvement
Updated: October 10, 2023
Fall 2023
The public works contract with American Construction has been executed. Due to long lead time for floats, on-site work will begin early January 2024. On-site Work will take about 2 months to complete. One float will be open at all times during construction.
The Army Corps of Engineers and National Marine Fisheries Service were confronted with several emergent priority projects (West Seattle Bridge) and regulatory changes which has slowed the permitting process. These agencies are now working through a large backlog of permit applications.
Some of the new federal rule changes are outlined here.
The permit, NWS-2018-1191-WRD - Don Armeni, has been under review since early June 2021 and has been moved forward for Endangered Species Act (ESA) consultation.
See permit drawings here.
The in-water work windows for Elliott Bay (July through December) will dictate the timing for in-water work. We will not shut the facility down during construction, we will replace the floats one side at a time. One Float will remain open during construction for launching and retrieval.
The Washington State Recreation and Conservation Office Boating Facilities Grant and Seattle Parks and Recreation fund this project.
Location
Don Armeni Boat Ramp, 1222 Harbor Ave SW, 98116
Budget
The Washington State Recreation and Conservation Office Boating Facilities Grant and Seattle Parks and Recreation fund this project.
Schedule
Design: Current
Bidding: Early 2023
Construction: Summer 2023
Project Description
Renovate existing failing two boat ramps. Scope of work includes, demolition of existing concrete abutment, pile driving and installation of steel piles, installation of new concrete abutment, procuring and installation of concrete floating docks and hardware.