You've probably noticed that the Hiawatha Place Staircase project has been paused for a while. Well, we're here to tell you that we are back at work! The stairs have mostly been formed. The rails will be installed soon. And electric components for lighting are being installed as well. We expect the entire project (stairs included!) to be complete in Q1 of 2024. We are looking forward to it, and hope you are too!
Check Out This Project's Progress
A view of the Staircase from Hiawatha Pl S
The Staircase, frrom the side.
One of the new Light Fixtures along the Moutains to Sound Trail.
The Mountains to Sound Trail, with a Light Fixture in place.
Overview
The Judkins Park light rail station is set to open in 2025. In preparation for this, in 2019 we asked the community how to make the area safer and more accessible. So we conducted the Judkins Park Station Access Study. We learned many things from it. For instance, the Mountains to Sound Trail needs more lighting to keep people who walk, run, roll, or bike safe. We can now confirm that all our changes reflect what the community wants and will complement the new light rail station. And with the money we received from the Sound Transit System Access Fund Program, we can construct these projects:
- ADA compliant upgrades to walking areas
- A new staircase on Hiawatha Pl S
- Lighting for the Mountains to Sound Trail
- Signalized pedestrian crossing at 23rd Ave S & S Grand St
Community Outreach
Visit this website if you want updates about the project. We will include our outreach materials in this section so you can see things like construction notices.
Project Map
Judkins Park New Trail Lighting and Hiawatha Stairway Connection
Map of the Mountains to Sound Trail winding through the Judkins Park area
Map Legend
![]() |
Existing lighting along trail |
![]() |
New Trail Lighting |
![]() |
Judkins Park station entrance |
![]() |
Hiawatha Stairway Connection |
Schedule
- Planning
- Fall 2019 - Spring 2021
- Design
- Spring 2021 - Fall 2022
- Construction (timeline subject to change based on weather conditions)
- Winter 2023 - Fall 2023
- Judkins Park Station Opening
- 2025
Funding
- Sound Transit System Access Fund Grant
- Levy to Move Seattle