East Marginal Way Corridor Improvement Project
Updated November 14, 2023
What's Happening Now?
We have finalized the water main pipe design and the contractor is in the process of ordering it and other materials needed for construction. Based on the procurement and delivery timelines for these items, we now anticipate construction will start as soon as early 2024. Once we have more specific information on material delivery, we will provide an updated construction start date and schedule.
Stay connected
Visit our project library at the bottom of this page to read more about project features and schedule, view our federal grant proposals, and look at design plans. Comments and questions are welcome by emailing EastMarginal@seattle.gov or calling (206)257-2263.
Overview
As Seattle grows, improvements to freight mobility are essential to promote regional and international economic competitiveness. East Marginal Way is a major freight corridor that provides access to the Port of Seattle terminals, rail yards, industrial businesses, and between local Manufacturing and Industrial Centers (MIC's). It is also a designated Heavy Haul Route, critical last-mile connector, and vital route for over-sized trucks or those carrying flammable cargo. In addition, the corridor provides a major connection for people who bike between the West Seattle Bridge Trail, downtown, and the SODO neighborhood.
This project will:
-
Improve safety and reliability in the movement of people and goods
-
Support freight loads by rebuilding East Marginal Way S to heavy haul standards
-
Promote efficiency through signal modifications, improving wayfinding and lighting, and intelligent transportation systems
-
Improve safety by separating non-motorized modes of traffic from vehicle traffic
Click here to view the latest design overview of the North Segment. The project reached final design in summer 2022 and we expect construction to begin as soon as early 2024.
Benefits
- Safety - Improved access and multimodal connections for all corridor users. Separated facilities for people walking and biking to reduce potential conflicts.
- Freight mobility - Support the economic vitality of our region by making it easier for freight to access the Port of Seattle and local industrial businesses.
- Efficiency - New and updated facilities for people walking and biking will improve access for transit. Signal modifications and intelligent transportation systems (ITS) will optimize travel for all corridor users.
Project segments
This project extends along East Marginal Way S from S Atlantic St to 1st Ave S. The project is divided in three segments – North, Central, and South. Each segment is moving at its own schedule based on funding we have secured for design and construction. The North segment of the East Marginal Way S project is now designed and moving into construction. The Central Segment is funded for design and unfunded for construction. The South Segment is unfunded for design and construction.
Select each segment below for more information about the design and schedule.
East Marginal Way Segments
North Segment
The North Segment runs from S Atlantic St to S Spokane St.
North Segment improvements will reduce conflicts between people biking and trucks accessing Port of Seattle driveways and increase safety and efficiency through the corridor. Design improvements include:
-
Reconstructing the East Marginal Way S roadway to heavy haul standards from approximately S Massachusetts St to S Spokane St
-
Protected bike lane separating non-motorized modes from freight traffic on the east side of East Marginal Way S between S Atlantic St and S Spokane St
-
Multi-use path on the west side of the street between S Horton St and S Spokane St
-
New signalized diagonal bicycle crossing at East Marginal Way S and S Horton St
-
Rebuilding the intersection and existing traffic signal at East Marginal Way S and S Hanford St
-
Revised curb radius with a truck apron at S Spokane St
-
New bike crossing with rapid flashing beacon (RRFB) at East Marginal Way S and S Massachusetts St
-
Replacing the existing water main in areas where the roadway will be reconstructed north of S Horton St
-
Rebuilding the sidewalk on the west side of East Marginal Way S adjacent to the roadway reconstruction north of S Horton St
-
Redesigning driveway at Terminal 25 South to improve visibility for people biking and driving
-
Dynamic message sign at S Alaska St and East Marginal Way S
-
Weigh-in-Motion system to help SDOT better understand wear and tear on our roadways and replace current spot-check enforcement system
The maps below show the current conditions and planned improvements between S Atlantic St and S Spokane St.
Existing conditions: S Atlantic St to S Massachusetts St
Planned improvements: S Atlantic St to S Massachusetts St
Existing conditions: S Hanford St to S Horton St
Planned improvements: S Hanford St to S Horton St
Existing conditions: S Horton St to S Spokane St
Planned improvements: S Horton St to S Spokane St
Central Segment
The Central Segment run from S Spokane St and Diagonal Ave S. It is funded for design and unfunded for construction. We will continue to pursue funding opportunities to construct the Central Segment.
This project aims to upgrade the Heavy Haul network, provide a clear route through the confusing area between S Spokane St and Diagonal Ave S, and construct a shared use trail to separate people walking and biking from motor vehicle traffic.
Freight improvements proposed in the Central Segment include reconstructing the surface street of East Marginal Way S to heavy haul standards between S Spokane St and Duwamish Ave S, improving wayfinding and lighting, and a Weigh-in-Motion system for northbound traffic at Duwamish Ave S. At the intersection of Diagonal Ave S, this project plans to realign the southwest corner to improve the turning radius for eastbound trucks making a right turn.
Our proposed design includes a shared use path west of the SR-99 viaduct on the east side of East Marginal Way S south of S Spokane St. At approximately mid-block, the path will cross to the west side of the street at a marked crosswalk, where it will continue to Duwamish Ave S. People walking and biking will use a marked crosswalk with flashing beacons to cross Duwamish Ave S and continue on the west side of East Marginal Way S past the concrete plant. The project will continue a wide shared use trail south to Diagonal Ave S.
South Segment
The South Segment runs from Duwamish Ave S to 1st Ave S. It is unfunded for both design and construction. We will continue to pursue funding opportunities to advance the South Segment, but currently do not have a schedule for this portion of the project.
The South Segment, from Duwamish Ave S to 1st Ave S, is part of State Route 99. There are no existing bike facilities or sidewalks on the west side of the street and sections of missing sidewalks on the east side of the street.
In March 2018, we completed a preliminary design for the South Segment that included:
- Pedestrian improvements at each existing traffic signal
- Constructing missing sidewalks on the east side of the street
- Bus stop improvements
- Signal enhancements where appropriate to improve predictability and safety for people walking and biking
We also developed a proposal to improve pedestrian and bicyclist connectivity to the 1st Ave S bridge. Design and construction of the South Segment is currently unfunded. We will continue to pursue funding opportunities to advance the South Segment, but currently do not have a schedule for this portion of the project.
Benefits
Funding
Funding to evaluate alternatives and complete early design was provided by the 9-year Levy to Move Seattle, approved by voters in 2015. Learn more about the levy at Levy to Move Seattle website. In 2019, we secured grants from Transportation Improvement Board (TIB) and Federal Highways (FHWA) to complete full design for the north and central segments. In November 2021, we secured remaining grant funding to construct the North Segment of the project. North Segment funding partners include:
- Freight Mobility Strategic Investment Board (FMSIB)
- Transportation Improvement Board (TIB)
- Port of Seattle
- Federal Highways (FHWA) funds from PSRC and RAISE
We continue to look for funds for construction of the Central Segment and to advance the South Segment design. Opportunities include state funding for highways and for non-motorized facilities, FMSIB, and other local transportation packages.
Segment | Design Funding | Construction Funding |
North | Yes | Yes |
Central | Yes | No |
South | No | No |
Schedule
This project began in 2015 and has advanced project planning and design through consistent engagement with community members, businesses, partner agencies, and community advocacy groups. We have secured funding to construct the North Segment of the project and expect to begin construction as soon as early 2024. Construction of the Central and South Segments will depend on identifying funding sources.
Planning phase (2015 - 2016)
-
Data collection and preliminary traffic analysis
-
Early design workshops
-
Community engagement through online open house and survey
Design phase (2017 - 2023)
-
North Segment design - completed summer 2022
- Central segment design - reached 90% design in summer 2023
-
Freight and bike community engagement survey
-
Briefings to community groups and bike detour workshop
-
Coordination with railroad agencies
-
Secured funds for North and Central Segment design and North Segment construction
Pre-construction of North Segment (2023)
- Potholing to locate utilities
- Ordered water main pipe
- Outreach to businesses
Construction of North Segment (Expected 2024- 2026)
-
Expect to begin construction as soon as early 2024
-
Community outreach during construction
-
Expect to complete construction in 2026
Public Engagement
We are committed to keeping you informed and involved throughout this project. Your questions and comments are always welcome by sending us an email at EastMarginal@seattle.gov or calling (206) 257-2263. To request a briefing for your organization or for more information, please send an email to EastMarginal@seattle.gov.
Project Materials
- North Segment factsheet (May 2022)
- 90% design rollplot (May 2022)
- Project factsheet (Updated October 2021)
- State Environmental Policy Act (SEPA) Documentation
- RAISE Grant Application (July 2021)
- Freight Survey SummaryPhase 1
- 90% Protected Bike Lane at S Horton St
- Phase 1 90% Terminal 25 South Driveway
- Design Rollplot
- US Department of Transportation BUILD grant
- 60% Frequently Asked Questions
- 60% Outreach Summary
- 60% Design Overview Phase 1
- 60% Design Plan Set (selected sheets)
- Phase 2 60% Design Plan Set (selected sheets)
- Project Fact SheetEast Marginal Way project
- INFRA grant, submitted 2/25/20